Energy project controls and scheduling
Scheduling and project controls for power generation, networks and renewables projects, including outages, overhauls and commissioning on operating plant. For asset owners and contractors.

Schedules built around outages, connections and commissioning
Outage windows, network connection dates and commissioning sequences are fixed constraints. The schedule has to be built around them from the start.
Commissioning-aware planning
Commissioning, energisation and handover sequenced in the schedule logic from the start.
Outage & connection windows
Planned outages, network connections and regulatory milestones managed as constraints, with mitigation visible before the window closes.
P6 on owner terms
Schedules built and updated to the owner's P6 standard: structure, codes, baselines and reporting.
From baseline through energisation
Most of our energy work is done as part of the project team, running the schedule and reporting cycle with them.
Assess the controls state
Review schedule, records and assurance expectations - mapping where the plan is silent, optimistic or contested.
Stand up the baseline
Baseline established or stabilised, commissioning logic integrated, and outage / connection constraints reflected in the master plan.
Run the weekly cycle
Status, lookahead, risk, EVM and reporting - owned alongside the project team, on the rhythm steering and the regulator expect.
Lift the team
Templates, training and documented procedures left behind so the in-house controls team can sustain the discipline.
Common pressure points on energy projects
These are the situations where a scheduler with energy experience makes the most difference.
Connection slips
A network connection date moves and the whole commissioning sequence has to be re-logic’d. The records made now decide what is recoverable later.
Outage overruns
A planned outage extends and the asset is unavailable past the agreed window. Quantum, EOT and operational exposure all move at once.
Assurance challenge
An independent reviewer challenges the schedule logic or the EVM baseline. The schedule and records need to answer the questions without being rebuilt.
What you should end up with
- A baseline aligned to commissioning and energisation milestones
- Outage and connection windows planned and tracked as constraints
- P6 schedules and reporting built to the owner's standard
- Progress records kept to support extension of time claims
Common questions about our energy work
Need scheduling support on an energy project?
Tell us about the project and what you need, whether that is a scheduler in the team, a programme or a review. A senior consultant will get back to you to talk it through.